Norwich Fire District — Source Protection Cost/Benefit
Risk-weighted, 30-year present-value comparison of recommended alternatives. TODO: dropdown of assumptions
Results
Expected total cost (lower is better)
Range of outcomes (Monte Carlo, 5,000 runs)
Table
| Alternative | Alt. cost (PV) | Expected event cost (PV) | Expected total (PV) | Benefit vs. do nothing | Net benefit | B/C ratio | P(pfas) in 30 yr | P(transpo) in 30 yr | P(fuel) in 30 yr |
|---|---|---|---|---|---|---|---|---|---|
| 1. Do nothing (excavator buys pit, no mitigation) | $0 | $124,950 | $124,950 | $0 | $0 | — | 45.5% | 3.0% | 45.5% |
| 2. Impervious slab / barrier (excavator buys pit) | $11,960 | $90,252 | $102,212 | $34,698 | $22,738 | 2.90 | 26.0% | 3.0% | 45.5% |
| 3. Install (3) monitoring wells on gravel pit | $83,683 | $66,128 | $149,812 | $58,822 | −$24,862 | 0.70 | 38.4% | 3.0% | 45.5% |
| 4. NFD to buy & conserve 10 acres of gravel pit | $209,201 | $14,566 | $223,767 | $110,384 | −$98,817 | 0.53 | 3.0% | 3.0% | 3.0% |
Benefit = expected contamination cleanup event cost avoided compared with Do-nothing scenario. B/C > 1 means the alternative pays for itself in avoided expected damages.
Global settings
Hazards
PFAS reaches the well
PFAS reaches well due to contaminated fill stored on gravel pit. Remediation would likely be at the treatment stage, using granular activated carbon (GAC).
Emergency event: spill on transportation corridor contaminates groundwater
High consequence, low probability event. Remediation cost considers District's share of emergency response, temporary water connection, sampling, and cleanup.
Fuel / hydraulic fluid spill from equipment stored on pit
A spill of diesel, gasoline, hydraulic fluid big enough to contaminate groundwater. Cleanup cost would fall on the repsonsible party under VT DEC rules.
Alternatives
1. Do nothing (excavator buys pit, no mitigation)
Benchmark scenario. Every other alternative is compared to this.
2. Impervious slab / barrier (excavator buys pit)
Reduces infiltration from stored materials, depends on owner upkeep.
3. Install (3) monitoring wells on gravel pit
Early warning: time to install treatment and/or act on the source before customers are exposed.
4. NFD to buy & conserve 10 acres of gravel pit
Removes the gravel-pit sources. Does not affect transportation corridor.